Bhartiya Garden Enclave Completion Date


Featured Image of Bhartiya Garden Enclave Completion Date

Bhartiya Garden Enclave (Nikoo Homes 8) is a very large residential project in North Bangalore, and construction is planned in different stages. As per the schedule, Phase 1 will be completed by 31 March 2031, and Phase 2 will be completed by 31 December 2031. The project is RERA registered on 7th May 2026, which means it follows all approved rules and legal building standards. It is spread across more than 12 acres of land and will be built step by step over a few years. These timelines clearly show the completion dates and possession dates, which help buyers plan their future home purchase and investment easily.

Bhartiya Garden Enclave Official RERA Details and Project Timeline


Understanding the RERA details and project timeline is important for anyone planning to buy a home in Bhartiya Garden Enclave (Nikoo Homes 8). RERA (Real Estate Regulatory Authority) makes sure that the project follows approved rules, proper construction process, and clear delivery timelines, which helps protect buyers.

Official RERA Registration Numbers

The project is RERA-approved in two different phases and has separate registrations for better clarity and transparency:

  • Phase 1 RERA No: PRM/KA/RERA/1251/309/PR/070526/008628
  • Phase 2 RERA No: PRM/KA/RERA/1251/309/PR/070526/008629

Project Timeline & Phasing

The project is planned in two phases and spread across around 12 acres, with homes and modern facilities built step by step.

Milestone  Phase 1 Details  Phase 2 Details 
Launch Date  7 May 2026  7 May 2026 
Land Area  7.53 Acres 4.46 Acres
Total Units  518 Units  518 Units 
Tower Structure  4 Towers (2B + G + 16 Floors) 5 Towers (2B + G + 24 Floors) 
Completion Date  March 31, 2031  December 31, 2031 
Possession Date  31 October 2031  31 March 2032 

Clear details about approvals, timeline, and schedule make it easier to understand the project progress and help in planning home purchase and investment decisions.

Current Construction Status of Bhartiya Garden Enclave: 2026 Update


As of May 2026, Bhartiya Garden Enclave (Also known as Nikoo Homes 8) is in the early stage of development after its official launch on 7th May 2026. Work has just started in a planned step-by-step way for both phase 1 and phase 2.

Phase 1 Construction Status

The Phase 1 construction of Bhartiya Garden Enclave (Nikoo Homes 8) will happen in a step-by-step manner, starting from land preparation and going up to final finishing work. The work starts in March 2026 and is expected to be completed by 31 March 2031.

1. Base Work (Foundation Stage)

  • Ground Work (Site Preparation): The team is currently clearing the land and leveling the ground to prepare the 11-acre site for construction. This work will go on from 31 March 2026 to 31 August 2026.
  • Foundation Work: The foundation of the towers will be built to make the buildings strong and safe. This work is planned from 31 July 2026 to 31 January 2027.
  • Retaining Walls & Strength Work: To keep the soil strong and stable, retaining walls and support structures will be built between July 2026 and August 2027.
  • Plinth Level Work: This is the stage where construction comes above ground level. The project will move to plinth work between 1 November 2026 and 31 August 2027.
  • Multi-Level Parking Construction: The basement and parking floors will be built in a later stage. This work is planned from 1 November 2028 to 31 July 2029.

2. Building Structure Work

  • RCC framework ( From 1 June 2027 to 31 July 2029): The main building structure is built.
  • Wall construction work (From 1 June 2027 to 31 July 2029): Walls inside the building are made.
  • Plaster work (From 1 August 2027 to 30 September 2029): Walls are made smooth.
  • Doors and windows work (From 1 October 2028 to 31 January 2031): Doors and windows are fixed.
  • Water, plumbing and electric work (From 1 September 2028 to 31 December 2030): Basic water and electricity setup is done.
  • Flooring and tile work (From 1 October 2028 to 31 January 2031): In this stage, the inside flooring work is done in all apartments and common areas.
  • Railings and grills work (From 1 October 2028 to 31 December 2030): In this stage, safety railings and metal grills are installed in important areas like balconies, staircases, and windows.

3. Finishing Works

  • Electric and plumbing finishing: This work will start from 1 October 2028 to 31 January 2031
  • Painting work: Starts from 1 October 2028 to 31 March 2031
  • Fire safety systems: Start from 1 September 2028 to 31 January 2031
  • Weather protection work: Starts from 1 October 2028 to 31 January 2031
  • Outside design and building look work: Starts from 1 October 2028 to 31 January 2031
  • Landscaping work: Starts from 1 July 2029 to 31 January 2031

Phase 2 Construction Status

Phase 2 of Bhartiya Garden Enclave will start a little later than Phase 1 and will continue till December 2031. The work will move step by step — first basic ground and foundation work, then building the high-rise structures, and finally full finishing work to make the homes ready for use.

  • Sub-Structure: Ground & Foundation Work

The first stage is site preparation and strong base building.

  • Earthwork & Leveling: Site cleaning and leveling start from 1 Jan 2027 to 30 Jun 2027.
  • Foundation & Retaining Walls: Strong base and wall support work starts on 1 May 2027, foundation finishes by Nov 2027, and retaining walls by Jun 2028.
  • Plinth & Parking Base: Ground level (plinth) work happens from Sep 2027 to Jun 2028. Special parking structure flooring is planned from Oct 2029 to May 2030.
  • Super-Structure: Tower Construction

It is the most visible stage of development where the 24-floor towers take shape and rise above the ground.

  • RCC Frame & Walls: Main building structure work runs from 1 Apr 2028 to 31 May 2030, where strong concrete frame and walls are built for the towers.
  • Plastering & Services: Wall finishing starts in June 2028, and work on electrical wiring, plumbing, and water supply begins in July 2029 for the full internal setup.
  • Doors, Windows & Flooring: Installation of doors, windows, tiles, and flooring happens from Aug 2029 to Nov 2031, making homes fully ready inside.
  • Finishing Works: Final Touches

This stage is the final stage where everything is completed so that homes become safe, beautiful, and ready for families to move in.

  • Electrical, Fire & Water Systems: The final setup of electric wiring, water supply, plumbing, and fire safety systems starts in mid-2029. All these works are completed by 30 Nov 2031, making sure the building is fully ready and safe to use.
  • Painting & Exterior Work: Painting of both inside walls and outside building surfaces begins in Aug 2029. This stage also improves the overall look of the towers, giving them a clean, finished, and modern appearance.
  • Landscaping & Outdoor Areas: Work on gardens, lawns, walking paths, and other open spaces starts in May 2030. All external development is completed by 30 Nov 2031, giving the project a fully finished and pleasant living environment.